1. After the machine is in place, it must be pressed and placed steadily, and fixed with anchor screws.
2. Before the test run, the inner cavity of the machine should be cleaned first, and the front cover should be locked with a star handle.
3. After turning on the power, pay attention to its phase sequence and make the main shaft rotate in the direction shown.
4. During the test run, pay attention to whether the machine has abnormal noises, so that the car can be checked in time.
5. Install the storage bag in the discharge hopper.